Guides / Basics
The process on one page
This is the order things normally happen in. Your own procedure may use slightly different words.
- 1. Appoint. The company names a Temporary Works Coordinator for the project, and Temporary Works Supervisors for the work.
- 2. Register. Each item of temporary works goes on a register.
- 3. Brief. A design brief tells the designer what they need to know.
- 4. Design and check. The designer designs it. A checker checks it, at a level suited to its complexity and risk.
- 5. Permit to proceed (where your procedure uses one). The go-ahead to start building.
- 6. Build and inspect. It is built to the design and inspected.
- 7. Permit to load. The coordinator's written go-ahead to load it.
- 8. Use and monitor. Regular inspections while it is in use.
- 9. Permit to unload. The go-ahead to take it out of use, strike it or remove it.
Permit names here follow BS 5975-1:2024. Some sites say permit to pour or permit to strike, but permit to load and permit to unload are the formal names.